Construction Impacts: June-July 2026

Planned Water Shutdowns

Temporary water shutdowns are currently anticipated in the Centralville project area for utility connection work:

  • June 30: Ennell Street at Hildreth Street
  • June 30: Lakeview Avenue at Bunker Hill Avenue
  • June 30: Willard Street near Market Basket
  • July 1: Willard Street at Beacon Street
  • July 8: Ludlam Street at Barker Street


Affected residents will be notified in advance whenever possible. Schedule is subject to change based on weather and construction conditions.

Traffic & Road Closures
Street / AreaLimitsStatusNotes
Bunker Hill AvenueLakeview Avenue to West Sixth StreetFull Road ClosureOngoing 24-hour closure for culvert, sewer, drainage, and water main installation. Detours remain in place.
W. 6th Street at Bunker Hill AvenueIntersection area24-Hour Closure AnticipatedCrews are targeting the week of July 13–17 for a 24-hour closure and detour. Exact timing is subject to change based on field conditions and construction progress.
VFW Parkway CorridorProject work areaTraffic Impacts ExpectedTraffic controls, temporary fencing, erosion controls, guardrail removal, and site preparation activities are expected in advance of future utility work.
Billings StreetProject work areaPartial Traffic ImpactsWater service work and utility activities are expected to continue. Expect delays near active work zones.
Ludlam StreetProject work areaPartial Traffic ImpactsWater service work is expected to continue. Intermittent traffic impacts may occur near active construction areas.
Willard StreetNear Market Basket and Beacon StreetPartial Traffic Impacts / Planned Water ShutdownsNew water main installation and related utility work are expected. Planned water shutdowns are anticipated in this area.
Hildreth StreetNear Ennell Street and adjacent work areasPartial Traffic Impacts / Planned Water ShutdownRock drilling, water main testing, disinfection, and related utility work are expected to continue.
Various LocationsProject AreaIntermittent Traffic ImpactsWater main testing, disinfection, utility commissioning, construction traffic, temporary detours, and parking restrictions may occur throughout the project area.