| VFW Highway | Drainage outlet work area near Bunker Hill Avenue | Active Construction / Traffic Pattern Changes | Restoration of VFW Highway and the drainage outlet area is expected the week of November 2. Changes to traffic management arrangements are scheduled November 9–20. Watch for updated signs and traffic patterns. |
| Bunker Hill Avenue | West Sixth Street to Hildreth Street | 24-Hour Road Closure / Active Construction | Sewer main, sewer and water service connections, and storm drain connections are expected November 2–4. Installation of the 6-by-5-foot drainage culvert is expected to resume November 5 and continue through November 20. |
| Worthen Street | Project work area | Water Utility Work | Installation of a 16-inch insertion valve is scheduled November 19–20. |
| Water Utility Work Areas | Specific locations not identified in the look-ahead | Water Valve Work / Underground Investigations | Backfilling around recently installed valves and connections is expected November 2–3. Excavation for additional 20-inch valve and pipe connection work is scheduled November 4–12. Test pits are expected November 13 and November 16–18. |
| Hildreth Street | Project work area | 24-Hour Road Closure / Active Construction | Installation of 60-inch stormwater pipe is scheduled November 4 and during the week of November 16. Sewer main, sewer and water service connections, and storm drain connections are expected November 5–13. Roads may remain closed when crews are not working. |
| Willard Street / Beacon Street / Twentieth Street | Project work area along this route | Stormwater Pipe Installation | Installation of 36-inch stormwater pipe is expected to continue throughout the three-week period. |
| Rock Work Areas | As needed within the project area | Drilling Complete / Possible Blasting | Rock drilling is complete. Blasting may occur as needed as underground work progresses. |
| Properties Affected by Water Shutdowns | Property-specific limits to be confirmed | Planned Water Service Interruptions | Water shutdowns are currently scheduled for November 4, November 12, and November 13. Residents and businesses should watch for updates and instructions specific to their property. |
| Various Locations | Throughout Centralville | Intermittent Traffic Impacts | Lane changes, detours, and parking restrictions may be present near active work areas. Follow posted signs and allow extra travel time. |