Construction Impacts: Week of October 5, 2026

Traffic & Road Closures
Street / AreaLimitsStatusNotes
VFW HighwayDrainage outlet work area near Bunker Hill AvenueActive Construction / Traffic Pattern ChangesRestoration of VFW Highway and the drainage outlet area is expected the week of November 2. Changes to traffic management arrangements are scheduled November 9–20. Watch for updated signs and traffic patterns.
Bunker Hill AvenueWest Sixth Street to Hildreth Street24-Hour Road Closure / Active ConstructionSewer main, sewer and water service connections, and storm drain connections are expected November 2–4. Installation of the 6-by-5-foot drainage culvert is expected to resume November 5 and continue through November 20.
Worthen StreetProject work areaWater Utility WorkInstallation of a 16-inch insertion valve is scheduled November 19–20.
Water Utility Work AreasSpecific locations not identified in the look-aheadWater Valve Work / Underground InvestigationsBackfilling around recently installed valves and connections is expected November 2–3. Excavation for additional 20-inch valve and pipe connection work is scheduled November 4–12. Test pits are expected November 13 and November 16–18.
Hildreth StreetProject work area24-Hour Road Closure / Active ConstructionInstallation of 60-inch stormwater pipe is scheduled November 4 and during the week of November 16. Sewer main, sewer and water service connections, and storm drain connections are expected November 5–13. Roads may remain closed when crews are not working.
Willard Street / Beacon Street / Twentieth StreetProject work area along this routeStormwater Pipe InstallationInstallation of 36-inch stormwater pipe is expected to continue throughout the three-week period.
Rock Work AreasAs needed within the project areaDrilling Complete / Possible BlastingRock drilling is complete. Blasting may occur as needed as underground work progresses.
Properties Affected by Water ShutdownsProperty-specific limits to be confirmedPlanned Water Service InterruptionsWater shutdowns are currently scheduled for November 4, November 12, and November 13. Residents and businesses should watch for updates and instructions specific to their property.
Various LocationsThroughout CentralvilleIntermittent Traffic ImpactsLane changes, detours, and parking restrictions may be present near active work areas. Follow posted signs and allow extra travel time.
Modernizing Infrastructure for a Resilient Centralville.