Upcoming Construction Schedule – Week of
July 13, 2026

Upcoming Construction Look-Ahead
Week Beginning July 13, 2026 

Weather permitting, construction activities for the Centralville Sewer Separation Project will continue throughout July as the City of Lowell advances critical infrastructure improvements to reduce flooding, improve sewer capacity, and protect the Merrimack River. 

Crews from Albanese D&S, Inc. and subcontractors will remain active throughout the Centralville neighborhood performing excavation, underground utility installation, water service connections, rock drilling, roadway preparation, water main testing, and construction of the new junction chamber along VFW Parkway. 

Where Work is Happening 

VFW Parkway Area 

Construction activities will continue along the VFW Parkway corridor as crews advance work on the new underground junction chamber and cast-in-place culvert. Residents may see excavation, hydraulic shoring, temporary fencing, erosion control, saw cutting, guardrail removal, and other site preparation activities. Water main testing and rebar, and formwork for the new structure are also expected to continue. 

Traffic Update: A temporary lane shift is now in place along VFW Parkway to safely accommodate construction. Motorists should reduce speeds, use caution, and follow posted traffic control signs while traveling through the area. 

Bunker Hill Avenue 

Work will continue on Bunker Hill Avenue between Lakeview Avenue and West Sixth Street as crews install new sewer, drainage, culverts, and water infrastructure. Water and sewer service connections will also continue throughout the corridor. 

Starting Monday, July 13, 2026 at 7:00 A.M. there will be a 24-hour closure of the intersection of West Sixth Street and Bunker Hill Avenue lasting until Friday, July 17, 2026 at 4:00 P.M. At which point the 24-hour closure of Bunker Hill Avenue between Lakeview Avenue and Homestead Road will begin and remain in effect while underground utility work continues. 

Barker Avenue 

Crews will continue installing new drainage infrastructure along Barker Avenue as construction progresses.  

Hildreth Street & Ludlam Street 

Rock drilling operations will continue on Hildreth Street and Ludlam Street as crews prepare for upcoming utility installation. Residents and motorists should expect intermittent construction noise and activity in these areas.  

Road Closures & Traffic Impacts 

Residents and commuters should continue to expect temporary lane shifts, detours, parking restrictions, and construction traffic near active work zones. 

Current traffic impacts include: 

  • Temporary lane shift on VFW Parkway  
  • 24-hour closure of the intersection of West Sixth Street and Bunker Hill Avenue the week of July 13, 2026. 
  • 24-hour closure of Bunker Hill Avenue between Lakeview Avenue and Homestead Road the week of July 20, 2026.  
What Residents May Notice 

During construction, residents may see: 

  • Excavation and junction chamber construction  
  • Sewer, drainage, culvert, and water main installation  
  • Water and sewer service connections  
  • Water main testing  
  • Rock drilling operations  
  • Temporary traffic controls, lane shifts, and detours  
  • Construction equipment and utility crews throughout the project area 


City staff and contractors will continue working to maintain safe access for residents, businesses, and emergency services whenever possible.
 

Looking Ahead 

These activities support upcoming sewer separation construction and stormwater improvements throughout Centralville. As construction progresses, work locations will continue to shift across the neighborhood. 

The public is encouraged to: 


Thank you for your continued patience as this important infrastructure work moves forward.
 

Modernizing Infrastructure for a Resilient Centralville.