Upcoming Construction Schedule – Week of
August 3, 2026
Upcoming Construction Look-Ahead
Week Beginning August 3, 2026
Where Work is Happening
VFW Parkway Area
Work will continue on the new underground junction chamber and cast-in-place culvert near VFW Parkway. Crews will be excavating, installing rebar and formwork, and pressure testing newly installed sections of water main. This is one of the largest components of the project and will remain an active work area throughout August.
Bunker Hill Avenue
Construction will continue on Bunker Hill Avenue between West Sixth Street and Hildreth Street as crews install a new culvert, sewer main, and underground utilities.
Water and sewer service connections will also continue between West Sixth Street and Lakeview Avenue. Residents may notice excavation equipment, utility crews, and temporary traffic controls throughout the corridor.
The 24-hour closure of Bunker Hill Avenue between Lakeview Avenue and West Sixth Street will remain in effect while underground utility work continues. West Sixth Street at Bunker Hill Avenue will also remain closed during active construction.
Kirk Street
Water main installation will continue on Kirk Street as crews work to upgrade the neighborhood’s water infrastructure.
Hildreth Street
Rock drilling will continue on Hildreth Street to prepare for underground utility installation.
Later in the construction period, controlled blasting is anticipated as crews work through ledge. Additional information will be shared with nearby residents before blasting begins.
Water Service Connections
Crews will continue connecting individual properties to the new water system on portions of Willard Street, Beacon Street, and Bunker Hill Avenue. These connections are an important step toward placing the new infrastructure into service.
Road Closures & Traffic Impacts
Drivers should continue to expect:
- Temporary lane shifts near active construction
- Short-term road closures or detours as work progresses
- Construction vehicles entering and leaving work zones
- Temporary parking restrictions in active work areas
Please slow down, follow posted signs, and use extra caution when traveling through construction zones.
Looking Ahead
Construction activities will continue progressing throughout Centralville as crews advance underground utility improvements and prepare for future sewer separation work. Active work locations will continue to shift throughout the neighborhood as each phase is completed.
We encourage the public to:
- Follow the project Facebook page
- Visit lowellwater.com for updates
- Sign up for email notifications
Thank you for your continued patience as this important infrastructure work moves forward.
Modernizing Infrastructure for a Resilient Centralville.