Upcoming Construction Schedule – Week of
August 31, 2026

Upcoming Construction Look-Ahead
Week Beginning August 31, 2026 

Weather permitting, construction will continue throughout Centralville as crews make progress on the City’s sewer separation project. 

During the next two weeks, crews are scheduled to work near VFW Parkway and along Beacon Street, Bunker Hill Avenue, Kirk Street, French Street, and Hildreth Street. Residents may encounter construction equipment, temporary traffic controls, parking restrictions, and road closures near active work areas. 

Where Work is Happening 

VFW Parkway Area 

Crews will continue building the new underground junction chamber near VFW Parkway, including work on the concrete structure, footings, and headwall. Additional construction activity is also scheduled in this area.  

Beacon Street and 20th Street  

Water service work is scheduled on Beacon Street from Monday, August 31, through Wednesday, September 2. 

A water shutdown is scheduled near 20th Street and Beacon Street on Thursday, September 3. Additional information will be provided directly to affected customers as it becomes available. 

Bunker Hill Avenue 

Crews will continue installing a new culvert and sewer pipe on Bunker Hill Avenue between West Sixth Street and Hildreth Street. Water and sewer service work is also scheduled between West Sixth Street and Lakeview Avenue. 

The 24-hour closure of Bunker Hill Avenue between Lakeview Avenue and West Sixth Street will remain in effect while underground utility work continues. West Sixth Street at Bunker Hill Avenue will also remain closed during active construction. 

Hildreth Street 

Rock drilling and controlled blasting will continue on Hildreth Street as crews prepare for and install a large, 60-inch reinforced concrete pipe. 

To safely accommodate this work, Hildreth Street will remain closed around the clock between Bunker Hill Street and Ludlam Street. This is an extended closure that is expected to remain in place throughout this phase of construction, rather than a temporary daytime or week-to-week closure. Additional updates will be provided as the work progresses, and a reopening timeline becomes available. 

Road Closures & Traffic Impacts 

Drivers should expect activity near construction areas, including construction vehicles, temporary traffic controls, parking restrictions, and possible short-term detours. Please slow down, follow posted signs, and allow extra travel time when traveling through active work zones. Specific road closure and detour information will be shared as it is confirmed. 

What Residents May Notice 

During construction, residents and travelers may see: 

  • Temporary lane shifts or short-term road closures 
  • On-street parking restrictions near active work areas 
  • Construction crews and equipment during daytime hours

City staff and contractors will work to maintain safe access for residents, businesses, and emergency services. 

Looking Ahead 

These activities support upcoming sewer separation construction and stormwater improvements throughout Centralville. As construction progresses, work locations will continue to shift across the neighborhood. 

The public is encouraged to: 

Thank you for your continued patience as this important infrastructure work moves forward. 

Modernizing Infrastructure for a Resilient Centralville.