Upcoming Construction Schedule – Week of
September 14, 2026

Upcoming Construction Look-Ahead
Week Beginning September 14, 2026 

Weather permitting, construction will continue throughout Centralville as crews make progress on the City’s sewer separation project. 

During the next three weeks, crews are scheduled to work near VFW Parkway and along Bunker Hill Avenue, Kirk Street, French Street, and Hildreth Street. Residents may encounter construction equipment, temporary traffic controls, parking restrictions, and road closures near active work areas.

Where Work is Happening 

VFW Parkway Area 

Work is expected to continue near VFW Parkway. During the week of September 14, crews anticipate working around the new underground junction chamber and outfall, including excavation and support work. Culvert installation is expected during the week of September 21, followed by additional work around the junction chamber and outfall during the week of September 28. 

This is expected to remain an active work area over the next several weeks.

Kirk Street and French Street  

Water main work is scheduled to continue along Kirk Street and French Street. 

Bunker Hill Avenue 

Crews are expected to continue installing a new culvert and 12-inch sewer pipe on Bunker Hill Avenue between West Sixth Street and Hildreth Street. 

Water and sewer service and catch basin work are also anticipated between West Sixth Street and Lakeview Avenue during the week of September 14. 

A 24-hour road closure is anticipated on Bunker Hill Avenue between West Sixth Street and Hildreth Street while culvert and sewer installation continues. Local residents will continue to  have vehicle access to these roads while construction takes place. 

Hildreth Street 

Rock drilling and controlled blasting will continue on Hildreth Street to prepare for underground pipe installation. 

Crews will also continue installing a 60-inch reinforced concrete pipe. A 24/7 road shutdown is identified in the contractor’s schedule while this work is underway.

Road Closures & Traffic Impacts 

Drivers should expect activity near construction areas, including construction vehicles, temporary traffic controls, parking restrictions, and possible short-term detours. Please slow down, follow posted signs, and allow extra travel time when traveling through active work zones. Specific road closure and detour information will be shared as it is confirmed.

What Residents May Notice 

During construction, residents and travelers may see: 

  • Temporary lane shifts or short-term road closures 
  • On-street parking restrictions near active work areas 
  • Construction crews and equipment during daytime hours

City staff and contractors will work to maintain safe access for residents, businesses, and emergency services. 

Looking Ahead 

These activities support upcoming sewer separation construction and stormwater improvements throughout Centralville. As construction progresses, work locations will continue to shift across the neighborhood. 

The public is encouraged to: 

Thank you for your continued patience as this important infrastructure work moves forward. 

Modernizing Infrastructure for a Resilient Centralville.

Discover more from

Subscribe now to keep reading and get access to the full archive.

Continue reading