Upcoming Construction Schedule – Week of November 16, 2026

Upcoming Construction Look-Ahead
Week Beginning November 16, 2026

Construction on the Centralville Sewer Separation Project is expected to continue over the next three weeks, through December 5, 2026. Crews will install drainage pipes, work on water and sewer lines, and pave sections of roadway. The dates below are estimates. Weather and conditions at the work site may change the schedule.

Thanksgiving Construction Schedule: No regular construction work is scheduled for Thursday, November 26, through Saturday, November 28, in observance of the Thanksgiving holiday.

Construction is expected to resume Monday, November 30.

Where Work Is Expected

VFW Highway and Lakeview Avenue

Crews will prepare for changes to the traffic pattern near VFW Highway from November 16–18.

Installation of a large drainage culvert near VFW Highway and Lakeview Avenue is expected to begin November 19 and continue into early December.

Bunker Hill Avenue

Crews expect to complete additional sewer and water service connections on November 18.

Installation of a large drainage culvert is scheduled to continue from November 19 into early December. Paving is also planned for November 16–17.

Hildreth Street and Barker Avenue

Crews will continue installing a large stormwater drainage pipe on Hildreth Street throughout the three-week period.

Paving on Hildreth Street is scheduled for November 18–19. Crews also expect to work on storm drain connections along Barker Avenue during those dates.

Additional drainage pipe installation on Hildreth Street is planned for December 3–5.

Father Morissette Boulevard and Nearby Streets

Several water main improvements are planned in this area:

  • November 16: Water valve work on Worthen Street.
  • November 17–20: Work to lower a water main near Tremont Place on Father Morissette Boulevard.
  • November 23–24: Additional water valve installation on Father Morissette Boulevard.
  • November 25: Small excavations to check underground conditions.
  • November 30–December 4: Work on a large water pipe crossing Father Morissette Boulevard.


Beacon Street to Twentieth Street

Crews will continue installing a large stormwater drainage pipe between Beacon Street and Twentieth Street throughout the three-week period.

Parkside Area

Work to remove and restore the rear entrance at Parkside is scheduled for November 20.

Road Closures & Traffic Impacts

VFW Highway Traffic Changes

Traffic patterns will change between Aiken Street and Bridge Street:

  • Beginning Monday, November 16: The inside lane in each direction will close. The outside eastbound and westbound lanes will remain open.
  • Beginning Thursday, November 19: Both westbound lanes and the westbound shoulder will close. Traffic will shift to the eastbound side, with one lane maintained in each direction. This pattern will remain until work on VFW Highway is complete.

Please allow extra travel time and follow posted signs and traffic controls.

The following 24-hour road closures are expected to remain in place during ongoing construction:

  • Bunker Hill Avenue: Between West Sixth Street and Hildreth Street.
  • Hildreth Street: Existing closure during underground pipe installation.

These roads may remain closed even when crews are not actively working, including overnight and on weekends.

Drivers may see lane changes, detours, and parking restrictions near work areas. Please slow down, follow posted signs, and allow extra travel time.

What Residents May Notice 

During construction, residents and travelers may see: 

  • Temporary lane shifts or short-term road closures 
  • On-street parking restrictions near active work areas 
  • Construction crews and equipment during daytime hours

City staff and contractors will work to maintain safe access for residents, businesses, and emergency services. 

Water Service

No planned water service shutdowns are currently listed for this three-week period.

If a water service interruption becomes necessary, affected residents and businesses will receive additional information.

Looking Ahead

These activities support upcoming sewer separation construction and stormwater improvements throughout Centralville. As construction progresses, work locations will continue to shift across the neighborhood. 

The public is encouraged to: 

Thank you for your continued patience as this important infrastructure work moves forward. 

Modernizing Infrastructure for a Resilient Centralville.